Question

1 Approved Answer

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification

A project team has just initiated a large project to move an organization's headquarters to another location. The risk manager has scheduled a risk identification session but
notices that the project charter, work breakdown structure (WBS). and scope statement are not available.
What should the risk manager consider?
Aligning with the project manager to hold an open brainstorm session with all stakeholders will suffice.
The ideal solution is to find alternate documents that provide good visibility on the environment.
Risk evaluation will be challenging without these elements as a frame of reference.
The risk identification process can be carried out as long as the project statement is available.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Fundamentals of Management

Authors: Robbins, DeCenzo, Coulter

7th Edition

132996855, 0-13-610982-9 , 9780132996853, 978-0-13-61098, 978-0136109822

More Books

Students also viewed these General Management questions