A project team is involved in detailed planning of their project, but the project management plan is not yet complete. They have information about one
A project team is involved in detailed planning of their project, but the project management plan is not yet complete. They have information about one similar project in the past, including how much that project cost. The team wants to leverage this information to create a cost estimate for their project. They will most likely use the __________ cost estimating methodology. Group of answer choices analogy parametric learning curve expert opinion