A project that provides annual cash flows of $12,600 for 12 years costs $67,150 today. At what rate would you be indifferent between accepting the
A project that provides annual cash flows of $12,600 for 12 years costs $67,150 today. At what rate would you be indifferent between accepting the project and rejecting it?
Please show how to calculate the NPV