A project that should have been 7 0 percent complete by now is only 5 5 percent complete. The total project budget is US$ 2
A project that should have been percent complete by now is only percent complete. The total project budget is US$ and the actual cost spent to date is US$
What is the scheduled performance index SPI and cost performance index CPI of this project?
A The SPI is and the CPI is
B The SPI is and the CPI is
C The SPI is and the CPI is
D The SPI is and the CPI is