Question

1 Approved Answer

A project that should have been 7 0 percent complete by now is only 5 5 percent complete. The total project budget is US$ 2

A project that should have been 70 percent complete by now is only 55 percent complete. The total project budget is US$210,000, and the actual cost spent to date is US$162,000.
What is the scheduled performance index (SPI) and cost performance index (CPI) of this project?
A) The SPI is 0.79, and the CPI is 0.71.
B) The SPI is 1.27, and the CPI is 0.98
C) The SPI is 0.82, and the CPI is 1.05
D) The SPI is 0.99, and the CPI is 0.96.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management Processes and Supply Chains

Authors: Lee J. Krajewski, Larry P. Ritzman, Manoj K. Malhotra

10th edition

978-013280747, 132807394, 9780132951814, 132807475, 132951819, 978-0132807395

More Books

Students also viewed these General Management questions