Question

1 Approved Answer

A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to

image text in transcribed
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to be running very low. A major milestone has been reached where the first two activities have been totally completed and the third activity is 75 percent complete. The planners were expecting to be only 55 percent through the third activity at this time. The first activity involves prepping the site for the bridge. It was expected that this would cost $1,435,000 and if was done for only $1,315,000. The second activity was the pouring of concrete for the bridge. This was expected to cost $10,515,000 but was actualiy done for $9,015,000. The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $8,515,000. To date. they have spent $5,015,000 on the superstructure. Calculate the schedule variance, schedule performance index, and cost performance index for the project to date. Note: Round your "performance index" values to 3 decimal places

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Foreign Corrupt Practices Act Compliance Guidebook Protecting Your Organization From Bribery And Corruption

Authors: Martin T. Biegelman, Daniel R. Biegelman

1st Edition

0470527935, 978-0470527931

More Books

Students also viewed these Accounting questions