. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this
. A project to develop technology training seminars is 5 days behind schedule at day 65. It had a planned cost of $735,000 for this point in time, but the actual cost is only $550,000. Estimate the schedule and cost variances. Re-estimate the variance if the actual cost had been $750,000 |
Step by Step Solution
There are 3 Steps involved in it
Step: 1