Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project was budgeted at R2, 000,000. The project is meanwhile being executed, and the following current figures have been assessed: PV: R 1 000,
- A project was budgeted at R2, 000,000. The project is meanwhile being executed, and the following current figures have been assessed: PV: R 1 000, 000 EV: R 700, 000 AC: R 1 100 000.The planned project duration is 12 months.
Required: Calculate the following:
- Cost Variance
- Schedule Variance
- Cost Performance Index
- Schedule Performance Index
- Estimate at completion (EAC) assuming that the cost variance was caused by one-time cost drivers, which are no more effective.
- Estimate at completion (EAC) if the cost drivers were not resolved and are still expected to influence the future.
- Estimate to Complete (ETC) assuming the one-time cost drivers were resolved.
- Determine the project status in terms of schedule and budget
- Revised project duration
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started