Question

1 Approved Answer

A project was budgeted at R2, 000,000. The project is meanwhile being executed, and the following current figures have been assessed: PV: R 1 000,

  1. A project was budgeted at R2, 000,000. The project is meanwhile being executed, and the following current figures have been assessed: PV: R 1 000, 000 EV: R 700, 000 AC: R 1 100 000.The planned project duration is 12 months.

Required: Calculate the following:

  1. Cost Variance
  2. Schedule Variance
  3. Cost Performance Index
  4. Schedule Performance Index
  5. Estimate at completion (EAC) assuming that the cost variance was caused by one-time cost drivers, which are no more effective.
  6. Estimate at completion (EAC) if the cost drivers were not resolved and are still expected to influence the future.
  7. Estimate to Complete (ETC) assuming the one-time cost drivers were resolved.
  8. Determine the project status in terms of schedule and budget
  9. Revised project duration

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Accounting Information Systems Thinking Development And Evaluation

Authors: Robyn L. Raschke, John A. Schatzel

1st Edition

1453396950, 9781453396957

More Books

Students also viewed these Accounting questions

Question

State four possible origins of planetary satellites, with examples.

Answered: 1 week ago