Question
A project was resource constrained, so the PM attempted to shuffle dates and resources. Given the network and resource profile above, select all the correct
A project was resource constrained, so the PM attempted to shuffle dates and resources. Given the network and resource profile above, select all the correct statements. (The process is WIP, so the PM may not be finished.)
A. The resources remained unchanged.
B. The proposed resource profile is still not feasible, the project cannot be implemented.
C. Not all activities are ES in the proposed network; some activities were delayed beyond their late starts.
D. In leveling, the end date was increased for the entire project.
E. The resources are leveled and the implementation is feasible.
F. Not all activities are ES in the proposed network; some activities were delayed within the LS limits.
G. The scheduled resource profile represents added resources.
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started