Question
1 Approved Answer
A project whose critical path has an estimated time of 58 days with a variance of 25 has a 35% chance that the project will
A project whose critical path has an estimated time of 58 days with a variance of 25 has a 35% chance that the project will be completed before day (rounded to nearest day). Select one: O 0.54 O b. Cannot be found 0.061 0 0.63 O 1.56 Previous Alat