A project will cost Rs 50,000 today. It is expected to generate cash flows of Rs 30,000, Rs 25,000 and Rs 15,000 each year through

  1. A project will cost Rs 50,000 today. It is expected to generate cash flows of Rs 30,000, Rs 25,000 and Rs 15,000 each year through year 1 to 3. The discount rate is 18 percent. Calculate the project's NPV and IRR.

    Year

    Cash Flow (Rs)

    0

    C0

    -50000

    1

    C1

    30000

    2

    C2

    25000

    3

    C3

    15000