Question

1 Approved Answer

A project will deliver $110 now, -$5 in a month's time, and -$30 in two month's time. The appropriate interest/discount rate is j12 = 3.600%

A project will deliver $110 now, -$5 in a month's time, and -$30 in two month's time. The appropriate interest/discount rate is j12 = 3.600% p.a. The Present Value (i.e period 0) of the ENTIRE cashflow delivered is:

options:

1)

$75.19

2)

$110.00

3)

$75.65

4)

$77.22

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Project Finance For Construction

Authors: Anthony Higham, Carl Bridge, Peter Farrell

1st Edition

1138941298, 978-1138941298

More Books

Students also viewed these Finance questions