A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is
A project's base case or most likely NPV is $44,000, and assume its probability of occurrence is 50%. Assume the best case scenario NPV is 85% higher than the base case and assume the worst scenario NPV is 35% lower than the base case.Both the best case scenario and the worst case scenario have a 25% probability of occurrence.Find the project's coefficient of variation.
I got 17.36...but I'm not quite sure this is correct =(