Answered step by step
Verified Expert Solution
Question
1 Approved Answer
A project's internal rate of return (IRR) is the compound rate that forces the PV of its inflows to equal its cost. The IRR
A project's internal rate of return (IRR) is the compound rate that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the YTM + on a bond. The equation for calculating the IRR is: CF1 = NPV CF0+ (1+n 1 IRR 0 = CF2 CFN + +... + = 0 N 2 (1 1+IRR (1 + IRR) CFt (1 + IRR) N t=1 CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal IRR If the IRR is less than the project's risk-adjusted cost of capital, then the project should be The IRR calculation assumes that cash flows are reinvested at the IRR Because of the IRR reinvestment rate assumption, when accepted; however, if the IRR is less than the project's risk-adjusted cost of capital, then the project should be accepted mutually exclusive projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR: differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the -Select- method should be used to evaluate projects. return Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%. 0 1 2 3 4 Project A Project B -1,300 -1,300 800 375 295 305 400 310 445 755 What is Project A's IRR? Do not round intermediate calculations. Round your answer to two decimal places. % What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places. % If the projects were independent, which project(s) would be accepted according to the IRR method?
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started