Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A project's internal rate of return (IRR) is the -Select- on a bond. The equation for calculating the IRR is: that forces the PV

image text in transcribed

A project's internal rate of return (IRR) is the -Select- on a bond. The equation for calculating the IRR is: that forces the PV of its inflows to equal its cost. The IRR is an estimate of the project's rate of return, and it is comparable to the -Select- + NPV = CF0+ CF1 CF2 + ... 1 2 (1 1 + IRR (1 N + IRR + (1 + CFN 1 + IRR N = 0 0 = = CFt t=1 (1 + IRR)* CFt is the expected cash flow in Period t and cash outflows are treated as negative cash flows. There must be a change in cash flow signs to calculate the IRR. The IRR equation is simply the NPV equation solved for the particular discount rate that causes NPV to equal -Select- The IRR calculation assumes that cash flows are reinvested at the -Select- . If the IRR is -Select- than the project's risk-adjusted cost of capital, then the project should be accepted; however, if the IRR is less than the project's risk-adjusted cost of capital, then the project should be -Select- Because of the IRR reinvestment rate assumption, when -Select- projects are evaluated the IRR approach can lead to conflicting results from the NPV method. Two basic conditions can lead to conflicts between NPV and IRR: -Select- differences (earlier cash flows in one project vs. later cash flows in the other project) and project size (the cost of one project is larger than the other). When mutually exclusive projects are considered, then the -Select- method should be used to evaluate projects. Quantitative Problem: Bellinger Industries is considering two projects for inclusion in its capital budget, and you have been asked to do the analysis. Both projects' after-tax cash flows are shown on the time line below. Depreciation, salvage values, net operating working capital requirements, and tax effects are all included in these cash flows. Both projects have 4-year lives, and they have risk characteristics similar to the firm's average project. Bellinger's WACC is 11%. 0 1 2 3 4 + 1 Project A Project B -1,300 -1,300 800 400 375 310 295 445 305 755 What is Project A's IRR? Do not round intermediate calculations. Round your answer to two decimal places. % What is Project B's IRR? Do not round intermediate calculations. Round your answer to two decimal places. % If the projects were independent, which project(s) would be accepted according to the IRR method? -Select- If the projects were mutually exclusive, which project(s) would be accepted according to the IRR method? -Select- Could there be a conflict with project acceptance between the NPV and IRR approaches when projects are mutually exclusive? -Select- The reason is -Select- Reinvestment at the -Select- is the superior assumption, so when mutually exclusive projects are evaluated the -Select- approach should be used for the capital budgeting decision. Check My Work (5 remaining)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image_2

Step: 3

blur-text-image_3

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles of managerial finance

Authors: Lawrence J Gitman, Chad J Zutter

12th edition

9780321524133, 132479540, 321524136, 978-0132479547

More Books

Students also viewed these Finance questions

Question

1. Critically discuss treatment approaches for violent offenders.

Answered: 1 week ago

Question

4 1 8 . .

Answered: 1 week ago

Question

What are the principal alloying elements in SAE 4340 steel?

Answered: 1 week ago