Question

...
1 Approved Answer

A project's progress is checked at month three of a total 12-month duration. The project's CPI is 0.9 and SPI is 1.1. What are these

A project's progress is checked at month three of a total 12-month duration. The project's CPI is 0.9 and SPI is 1.1. What are these index results telling the Project Manager about the project's progress in terms of cost and time (2 Marks)

After analysing cost and time progress to date the project is often re forecasted to determine the new Estimate at Completion. The forecast can be done by either using a 'typical' or 'atypical approach. What are the differences in each approach (3 Marks)

Identify two tools (methods) for getting a time constrained project back on schedule when it is identified the project will be late. Discuss the relative merits (advantages and disadvantages) of your solutions (5 Marks)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Physics

Authors: Alan Giambattista, Betty Richardson, Robert Richardson

2nd edition

978-0077339685

Students also viewed these General Management questions

Question

in a table

Answered: 1 week ago

Question

solve by LCM Method:+ DIT x-1 x-3

Answered: 1 week ago