Question
1 Approved Answer
A resource's maximum units value does not prevent a resource from becoming overallocated, but Project indicates when the resource's assignments exceed the resource's maximum units
A resource's maximum units value does not prevent a resource from becoming overallocated, but Project indicates when the resource's assignments exceed the resource's maximum units capacity. Group of answer choices True False