A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well
A risk manager has noticed that response actions are not working as expected when a risk occurs, mainly because the risk triggers are not well defined Which tool should the risk manager use to fecilitate risk trigger identification in the upcoming risk review assessment? Affinity diagram Ishikawa diagram Risk breakdown structure (RBS) Risk burndown chart
Step by Step Solution
There are 3 Steps involved in it
Step: 1