A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity
A risk manager reviews a Monte Carlo schedule risk analysis model before sharing the results with the project manager. The risk manager notices that activity correlations were not included in the model. What is an effect of adding the correlation to the model? Increases the standard deviation of the model. Increases the probability of correlated activities finishing on time. Reduces the project completion duration. Allows more risks to be included in the model