A road is to be constructed. The following are the costs for one of the alternatives. . Construction cost $3,500,000 Maintenance cost $25,000 every two
A road is to be constructed. The following are the costs for one of the alternatives. . Construction cost $3,500,000 Maintenance cost $25,000 every two years Renovation cost-125,000 every 10 years Find the capitalized cost if the interest rate is 8%