A Schedule Perfomance Index (SPI) of 1.2 means the project is; Select one: a. Under Budget b. Ahead of Scheulde c. Behind Schedule d. Over

A Schedule Perfomance Index (SPI) of 1.2 means the project is;

Select one:

a. Under Budget

b. Ahead of Scheulde

c. Behind Schedule

d. Over Budget