A schedule recovery plan from the contractor is required by the CM if: A . Concurrent contractor and owner delays arise B . A time
A schedule recovery plan from the contractor is required by the CM if:
A Concurrent contractor and owner delays arise
B A time extension request is submitted
C Delays occur that are the responsibility of the contractor
D The owners scope of work changes