A scheduler's job is to take outputs from S&OP, aggregate planning, MRP and MPS and to make this data usable to the organization in the

A scheduler's job is to take outputs from S&OP, aggregate planning, MRP and MPS and to make this data usable to the organization in the form of a production schedule. Based on this production schedule other departments can plan human resources, maintenance etc.

Based on the supplied Master Production Schedule and production constraints build a daily (by shift) breakfast cereal production schedule for six weeks in 2020 by line by product.

  • A summary as to your thinking and strategy. Why did you choose this particular strategy? Do you have any conclusions regarding the schedule?
  • Percentage of demand in total, by family and by sku that you produced by this plan
  • The number of changeovers that were necessary to complete your plan
  • The total dollar contribution if you were able to produce every case and the percentage of that which was actually produced

Version 1 instructions:

  • Choose four of the five production lines to create production plans
  • Create a by shift by day by sku (stock keeping unit) by line production plan for the six weeks beginning in mid-November (the 16th) and running through to the start of Christmas holidays beginning on December 24.
  • You must not exceed line capacity
  • If you have two weeks in a month to schedule remember to split the monthly volume
  • You may encounter situations where you have too much or too little capacity; in the latter it will be up to you to determine priority skus to produce
  • Complete the assignment using the Excel template provided

Version 1 constraints:

  • Due to freshness concerns one can only build inventory six weeks in advance
  • Families need to be run together
  • The plant runs 3 shifts a day 5 days a week. Overtime is available, but overtime costs 1.5 times more than regular shifts and the plant is restricted to two overtime shifts a week
  • Due to Christmas vacation the plant is down the last week of December
  • Due to Family Day, there is a vacation day the third Monday of February
  • Due to Thanksgiving, there is a vacation day the second Monday of October
  • There is one cleaning shift per week, typically the last shift of the week
  • Line 1 is down for one week in November for Maintenance
  • Line 2 is down for one week in January for Maintenance
  • Line 3 is down for one week in October for Maintenance
  • Line 4 is down for one week in February for Maintenance
  • Line 5 is down for one week in March for Maintenance

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Strategic Management and Competitive Advantage Concepts and Cases

Authors: Jay B. Barney, William Hesterly

5th edition

133129306, 0133127400, 9780133129304, 978-0133127409

More Books

Students also viewed these General Management questions

Question

Write a Python program to check an input number is prime or not.

Answered: 1 week ago

Question

Write a program to check an input year is leap or not.

Answered: 1 week ago

Question

Write short notes on departmentation.

Answered: 1 week ago