A scrum master is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete.
A scrum master is responsible for estimating a work package that has a significant amount of uncertainty associated with the time and cost to complete. Due to the uncertainty involved he will be making a low, an average and a high estimate. He is using which estimating approach?