a Shan Co is considering a four-year project that will require an initial investment of $7,000. The base-case cash flows for this project are projected to be $12,000 per year. The best-case cash flows are projected to be $20,000 per year, and the worst-case cash flows are projected to be - $1,000 per year. The company's analysts have estimated that there is a 50% probability that the project will generate the base-case cash flows. The analysts also think that there is a 25% probability of the project generating the best-case cash flows and a 25% probability of the project generating the worst-case cash flows. What would be the expected net present value (NPV) of this project if the project's cost of capital is 11%? O $28,986 $26,351 $22,398 $27.669 Shan now wants to take into account its ability to abandon the project at the end of year 2 of the project ends up generating the worst-case scenario cash flows. Ir it decides to abandon the project at the end of year 2, the company will receive a one-time net cath innow of $4,750 (at the end of year 2). The $4,750 the company receives at the end of year 2 is the difference between the cash the company receives from selling off the project's assets and the company's -$1,000 cash outflow from operations. Additionally, if it abandons the project, the company will have no cash flows in years. 3 and 4 of the project Using the information in the preceding problem, find the expected NPV of this project when taking the abandonment option into account Shan now wants to take into account its ability to abandon the project at the end of year 2 if the project ends up generating the worst-case scenario cash flows. If it decides to abandon the project at the end of year 2, the company will receive a one-time net cash inflow of $4,750 (at the end of year 2). The $4,750 the company receives at the end of year 2 is the difference between the cash the company recelves from selling off the project's assets and the company's -$1,000 cash outflow from operations, Additionally, if it abandons the project, the company will have no cash flows in years 3 and 4 of the project Using the Information in the preceding problem, find the expected NPV of this project when taking the abandonment option into account $33,438 $27,865 $26,472 $32,045 What is the value of the option to abandon the project? Grade It Now Save & Continue