A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. All jobs can be split in half at both
A shoe repair operation uses a two-step sequence that all jobs in a certain category follow. All jobs can be split in half at both stations. For the group of jobs listed:
JOB TIMES (minutes) | |||||
A | B | C | D | E | |
Workstation A | 27 | 18 | 70 | 26 | 15 |
Workstation B | 45 | 33 | 30 | 24 | 10 |
Click here for the Excel Data File
a. Find the sequence that will minimize total completion time.
b. Determine the amount of idle time for workstation B.