Question
A simple project listing of five activities, their predecessors, and their respective time estimates are presented below: Activity Immediate Predecessor Time in Days A None
A simple project listing of five activities, their predecessors, and their respective time estimates are presented below:
Activity | Immediate Predecessor | Time in Days |
A | None | 2 |
B | A | 2 |
C | A | 1 |
D | B and C | 3 |
E | D | 1 |
Using the CPM, which activities have slack in this project?
Step by Step Solution
3.54 Rating (154 Votes )
There are 3 Steps involved in it
Step: 1
1 D A B D E ACTIVITY DURATION ES EF LS LF SLACKLFEF CRI...Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get StartedRecommended Textbook for
Transport Operations
Authors: Allen Stuart
2nd Edition
978-0470115398, 0470115394
Students also viewed these General Management questions
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
Question
Answered: 1 week ago
View Answer in SolutionInn App