1 Approved Answer
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here: Activity Immediate Predecessor Time in Days A None
A simple project listing of five activities, their predecessors, and their respective time estimates are presented here:
Activity Immediate Predecessor Time in Days
A None
B A
C A
D B and C
E D
Using the CPM which activities have slack in this project?
Multiple Choice
A
B
C
D
C and E