A small accounting company needs to update and extend its existing time recording system. You are the project manager and have drawn up an outline
A small accounting company needs to update and extend its existing time recording system. You are the project manager and have drawn up an outline project plan for the main project activities, as follows. You are required to prepare Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). Also show the slack(s) if any. Do this on paper
Activity | Time Duration | Dependency |
A | 6 | -- |
B | 2 | -- |
C | 2 | -- |
D | 3 | -- |
E | 8 | A |
F | 5 | B, E |
G | 9 | C, F, D |
H | 3 | -- |
I | 2 | P, H |
J | 3 | B, E |
K | 10 | G |
L | 1 | D |
M | 10 | I, J, K |
N | 3 | L, Q |
O | 5 | M, N |
P | 4 | A |
Q | 5 | G |
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started