A small accounting company needs to update and extend its existing time recording system. You are the project manager and have drawn up an outline

A small accounting company needs to update and extend its existing time recording system. You are the project manager and have drawn up an outline project plan for the main project activities, as follows. You are required to prepare Program Evaluation Review Technique (PERT) and Critical Path Method (CPM). Also show the slack(s) if any. Do this on paper

Activity Time Duration Dependency
A 6 --
B 2 --
C 2 --
D 3 --
E 8 A
F 5 B, E
G 9 C, F, D
H 3 --
I 2 P, H
J 3 B, E
K 10 G
L 1 D
M 10 I, J, K
N 3 L, Q
O 5 M, N
P 4 A
Q 5 G

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

More Books

Students also viewed these Accounting questions

Question

Can options that are written qualify for hedge accounting?

Answered: 1 week ago