Question

1 Approved Answer

A small assembly line for the assembly of power steering pumps needs to be balanced. The precedence diagram is shown below. The cycle time is

A small assembly line for the assembly of power steering pumps needs to be balanced. The precedence diagram is shown below.

  • The cycle time is determined to be 1.9 minutes. How would the line be balanced by choosing the assignable task having the longest task time first? Fill in the table below. If your answer is zero, enter "0". Round your answers to one decimal place.

    Station

    Tasks

    Total Time

    Idle Time

    1

    B,A,C,D

    ?

    ?

    2

    E,F

    ?

    ?

    3

    G,H,I

    ?

    ?


    Total

    ?

    ?


    • What is the assembly-line efficiency? Round your answer to one decimal place.

0.3 (A) 0.8 B 0.3 0.1 (D) 0.6 0.5 (E) 1.1 (H) 110.7 0 0.1

Step by Step Solution

3.42 Rating (165 Votes )

There are 3 Steps involved in it

Step: 1

03 08 B 3 25 1 01 14 2 03 BACD E F G H I Total Line efficie... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

OM operations management

Authors: David Alan Collier, James R. Evans

5th edition

1285451376, 978-1285451374

More Books

Students also viewed these Management Leadership questions

Question

What chemical events occur during the digestion of food?

Answered: 1 week ago