A small sample of your project's PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for

A small sample of your project's PERT calculations is shown here. Activity 2 is particularly important to the project, and your stakeholders are asking for a confidence level for this activity. You tell them there is a 95.44 percent chance of completing activity 2 within how many days?

Activity

Optimistic

Pessimistic

Likely Expected Value

1

10

14

12

2

20

30

23

3

3

3

3

a.

Between 21 and 25 days

b.

Between 13 and 33 days

c.

Between 18 and 28 days

d.

Between 23 and 28 days

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Hospitality Management Strategies

Authors: Ronald A Nykiel, Ronald A CHE CHA Nykiel PhD

1st Edition

0130618764, 9780130618764

More Books

Students also viewed these General Management questions