Question

1 Approved Answer

A software development effort was estimated to address 10 requirements, with 1K SLOC per requirement, a 60% ESLOC conversion factor, and 1.0 hrs/ESLOC productivity, for

A software development effort was estimated to address 10 requirements, with 1K SLOC per requirement, a 60% ESLOC conversion factor, and 1.0 hrs/ESLOC productivity, for a total effort of 6,000 hours. Over the course of development, 2 additional requirements were added; 1.5K SLOC were needed to address each requirement; the ESLOC conversion factor rose to 80%; and final productivity was 1.1 hrs/ESLOC, resulting in a total effort of 15,840 hours. What was the cost growth factor due to Reuse optimism (independent of other factors)?

a 1.10

b 1.50

c 1.33

d 1.20

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Principles Of Financial Accounting

Authors: Jerry J. Weygandt, Michael J. Atkins, Donald E. Kieso, Paul D. Kimmel, Valerie Ann Kinnear, Barbara Trenholm, Joan E. Barlow

1st Canadian Edition

ISBN: 1118757149, 978-1118757147

More Books

Students also viewed these Accounting questions