A software project requires 75,000 lines of code, 35 percent of which are procedural statements written at an average of 45 minutes each line and
A software project requires 75,000 lines of code, 35 percent of which are procedural statements written at an average of 45 minutes each line and the remaining 65 percent are operational software, which takes 2.5 hours per line to write. The costing rate of the programmers is $50.00 per hour. What is the cost of this project? Show your calculations.