A soil sample was taken from a proposed cut area in a highway construction project and sent to a soils laboratory for a compaction test,

A soil sample was taken from a proposed cut area in a highway construction project and sent to a soils laboratory for a compaction test, using the Standard Proctor compaction procedure. Results of the test are as follows:
Maximum dry unit weight = 112.6 lb/ft^3
Optimum moisture content = 15.5%
The contractor, during construction of the soil embankment, achieved the following:
Dry unit weight reached by field compaction = 107.1 lb/ft^3
Actual water content = 16.0%
Determine the percent compaction achieved by the contractor.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

An Introduction to Geotechnical Engineering

Authors: Robert D. Holtz, William D. Kovacs, Thomas C. Sheahan

2nd edition

132496348, 978-0132496346

More Books

Students also viewed these Civil Engineering questions

Question

W0hat signs of aggression and assertiveness are evident?

Answered: 1 week ago

Question

What themes recur?

Answered: 1 week ago

Question

What phase of group process does the group seem to be in?

Answered: 1 week ago