Question
1 Approved Answer
A stakeholder on your project asks to see the top 10 risk list. Your project sponsor says not to share the list because it is
A stakeholder on your project asks to see the top 10 risk list. Your project sponsor says not to share the list because it is sensitive information. What do you do? You do not show it to the stakeholder because this is a secret list. You show it to the stakeholder because the top 10 list is a tool to help the team manage risks; thus, it can and should be shared. You show only the top two risks to the stakeholder. You show the list to the stakeholder but keep it a secret from the company