A student named Saada wants to use the CPM method to analyze a project schedule. She was able to obtain the following information. Draw the network diagram using the AON format (activity on node). Calculate ES/EF/LS/LF/slack for all activities. activity Immediate predecessor(s) Duration (days) A None 2 B A 3 C A 4 D B,C 3 E D 7 F D 3 G E,F 5