A student named Saada wants to yse CPM method to analyze a project schedule. 1. A student named Saada wants 'to use the CPM method
A student named Saada wants to yse CPM method to analyze a project schedule.
1. A student named Saada wants 'to use the CPM method to analyze a project schedule. She was able to obtain the 'following information. Draw the network diagram using the AON format (activity on node). Calculate ES/EF/LS/LF/slack for all activities. activi c Immediate None Duration da s 2 3 4 3 7 3 5