A subcontractor can produce 100 units per month and 25% more per month with overtime. The production planner submits an 18 month plan showing the
A subcontractor can produce 100 units per month and 25% more per month with overtime. The production planner submits an 18 month plan showing the subcontractor producing 130 units the last 6 months of the time horizon. a. The plan violates a constraint b. The plan is accounting for supply uncertainty. c. The plan shows demand uncertainty in the outer months d. The plan is building inventor