A subcontractor informs the PM that there is a slippage in its work schedule by at least two weeks. This work is thought to be

A subcontractor informs the PM that there is a slippage in its work schedule
by at least two weeks. This work is thought to be on the critical path of the
project. The PM should do all of the following except:
a. Review the contract to determine the subcontractors obligation to meet
the current schedule
b. Negotiate an add-on to the project to bring the schedule back in line.
c. Review the project master schedule to determine if there indeed will be a
two-week impact on the project
d. Review the subcontractors schedule to determine whether there is an
actual two-week delay.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Early Entrepreneurship Everything You Need To Start Early

Authors: Dhruvv Lohia

1st Edition

979-8889759683

More Books

Students also viewed these General Management questions

Question

What clear examples of ethical lapses do you find in these cases?

Answered: 1 week ago