Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A subcontractor needs to install flooring. In the area has old vinyl tile, it must be removed and replaced by with new vinyl tile. Additionally,

A subcontractor needs to install flooring. In the area has old vinyl tile, it must be removed and replaced by with new vinyl tile. Additionally, the concrete slab needs to be topped with ceramic tile. This simple project is broken into the activities shown in the following table:

Activity ID Activity Description Predecessor Duration (Day) Labor
A Purchase & delivery materials - 5 2
B Remove old vinyl tile - 7 4
C Install ceramic tile A 3 3
D Install new vinyl tile A, B 5 3
E Clean-up & inspect C, D 2 2

  1. Draw the resource histogram based on early start schedule.
  2. If the maximum number of labors available to utilize each day is 4, does the subcontractor able to accomplish this project on time? Show all your calculations.
  3. Level the resource so that the subcontractor does not use more than 6 labors at each day.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

Lets break down the question into the specific tasks and provide detailed answers 1 Draw the Resource Histogram Based on Early Start Schedule To draw ... blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Operations Management

Authors: William J Stevenson

12th edition

2900078024107, 78024102, 978-0078024108

More Books

Students also viewed these General Management questions