Question
A. Suppose a company has proposed a new 4-year project. The project has an initial outlay of $34,000 and has expected cash flows of $8,000
A.
Suppose a company has proposed a new 4-year project. The project has an initial outlay of $34,000 and has expected cash flows of $8,000 in year 1, $9,000 in year 2, $10,000 in year 3, and $14,000 in year 4. The required rate of return is 15% for projects at this company. What is the net present value for this project? (Answer to the nearest dollar.)
B.
Suppose a company has two mutually exclusive projects, both of which are three years in length. Project A has an initial outlay of $6,000 and has expected cash flows of $2,000 in year 1, $5,000 in year 2, and $5,000 in year 3. Project B has an initial outlay of $7,000 and has expected cash flows of $3,000 in year 1, $4,000 in year 2, and $5,000 in year 3. The required rate of return is 16% for projects at this company. What is the net present value for the best project? (Answer to the nearest dollar.)
Step by Step Solution
There are 3 Steps involved in it
Step: 1
Get Instant Access to Expert-Tailored Solutions
See step-by-step solutions with expert insights and AI powered tools for academic success
Step: 2
Step: 3
Ace Your Homework with AI
Get the answers you need in no time with our AI-driven, step-by-step assistance
Get Started