Question

1 Approved Answer

A SW company with CMMI = 1 is hired on a project where the project team gets along perfectly well, the company is totally familiar

A SW company with CMMI=1 is hired on a project where the project team gets along perfectly well, the company is totally familiar with the application, there is no client involvement, a very thorough risk analysis has been implemented.
a) Given that 17 attributes are considered in estimating the SW effort, what COCOMO II model is used to estimate the effort?
b) Calculate the exponent term B considering the first sentence of the question!
c) At the end of the project, SW effort estimated, Eest, is found to be 20% less than the actual effort, Eact, i.e.,eE={|Eact}|)/(Eact**. Given that E=A** size ?B**M and Mest=0.85Mact, what is the percent error, esize, in the SW size?
d) What would be esize if Mest=0.8Mact? What conclusions would you draw from such a result?
Hint: eE denotes the percent error in effort; A and M denote, in respective order, the constant factor and the multiplier in the SW effort estimation formula.
Note that to get any points you have to show the correct calculations for both parts (b) and (c). No points for only correct results with no or incorrect calculations!!! PLEASE B PART SOLUTON.
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Students also viewed these Databases questions

Question

Am I just skimming over the problem?

Answered: 1 week ago