A switchboard is assembled in four operator-attended operations whose normal times are 0.55, 0.84, 1.10, and 0.75 hr., respectively. Each operator works, including overtime, no
A switchboard is assembled in four operator-attended operations whose normal times are 0.55, 0.84, 1.10, and 0.75 hr., respectively. Each operator works, including overtime, no more than 2200 hr. per