Question

1 Approved Answer

A table is assembled using three components, as shown in the following product structure tree. The company that makes the table wants to ship 2

A table is assembled using three components, as shown in the following product structure tree. The company that makes the table wants to ship 200 units at the beginning of day 4,260 units at the beginning of day 5, and 320 units at the beginning of day 7. Receipts of 200 wood sections are scheduled at the beginning of day 2. There are 240 legs on hand. An additional 20 percent of the order size on legs is added for scrap allowance. There are 80 braces on hand. Lead time (in days) for all items is a function of each order quantity and is shown below.
Order Quantity Lead Time (days)
13201
3218002
8011,5503
Prepare the material requirements plan using lot-for-lot ordering. (Do not leave any empty spaces; input a 0 wherever it is required.)
Production Schedule
Day Beg. Inv. 1234567
Quantity 200260320

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Global Strategy

Authors: Mike W. Peng

5th Edition

0357512367, 978-0357512364

Students also viewed these General Management questions