Question

1 Approved Answer

A table is assembled using three components, as shown in the following product structure tree. The company that makes the table wants to ship 8

A table is assembled using three components, as shown in the following product structure tree. The company that makes the table wants to ship 80 units at the beginning of day 4,120 units at the beginning of day 5, and 160 units at the beginning of day 7. Receipts of 80 wood sections are scheduled at the beginning of day 2. There are 110 legs on hand. An additional 20 percent of the order size on legs is added for scrap allowance. There are 50 braces on hand. Lead time (in days-for all items is a function of each order quantity and is shown below.
\table[[Order Quantity,Lead Time (days)],[1-160,1],[161-360,2],[361-800,3]]
Prepare the material requirements plan using lot-for-lot ordering. (Do not leave any empty spaces; input a 0 wherever it is required.)
\table[[Beg Production Schedule],[\table[[Day],[Quantity]],Beg. Inv.,1,2,3,\table[[4],[80]],\table[[5],[120]],6,\table[[7],[160]]]]
Table (*Variable LT)
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Planned-order releases
Wood Sections
Gross requirements
Scheduled receipts
Projected on hand
Net requirements
Planned-order receipts
Beg. Inv.
1
3
4,5
5
image text in transcribed

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access with AI-Powered Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Thomas Calculus Early Transcendentals

Authors: Joel R Hass, Christopher E Heil, Maurice D Weir

13th Edition

978-0321884077, 0321884078

Students also viewed these General Management questions