Answered step by step
Verified Expert Solution
Link Copied!

Question

1 Approved Answer

A task was timed for 60 cycles. It took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance

A task was timed for 60 cycles. It took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance is 12 percent. Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.) a. Observed time b. Normal time c. Standard time minutes minutes minutes
image text in transcribed
A task was timed for 60 cycles, it took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance is 12 percent Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Organizational Behavior

Authors: Andrzej A. Huczynski, David A. Buchanan

8th Edition

978-0273774815

Students also viewed these General Management questions