A task was timed for 60 cycles. It took an average of 1.32 minutes per cycle. The performance rating was 100 percent, and workday allowance
A task was timed for 60 cycles. It took an average of 1.32 minutes per cycle. The performance rating was 100 percent, and workday allowance is 6 percent. Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.) a. Observed time b. Normal time c. Standard time