A task was timed for 60 cycles. It took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance

A task was timed for 60 cycles. It took an average of 1.25 minutes per cycle. The performance rating was 94 percent, and workday allowance is 12 percent. Determine each of the following. (Do not round intermediate calculations. Round the final answers to 2 decimal places.) a. Observed time b. Normal time c. Standard time minutes minutes minutes
image text in transcribed
A task was timed for 60 cycles it took an average of 125 minutes per cycle. The performance rating was 94 percent, and workday allowance is 12 percent. Defermine esch of the following (Do not round imermediate caleulations, Round the finnt onswors to 2 decimal plnces.)

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

Successful Time Management

Authors: Patrick Forsyth

Chinese 1st Edition

7508679814, 978-7508679815

More Books

Students also viewed these General Management questions