A TCPI of 1.10 would mean ____. Multiple choice question. the project is ahead of budget, and is earning $1.10 in value for each dollar
A TCPI of 1.10 would mean ____. Multiple choice question. the project is ahead of budget, and is earning $1.10 in value for each dollar spent. each remaining dollar in the budget must earn $1.10 in value to complete the project on time. the work must be finished 10% sooner for the project to finish on time