A team has 100 story points in the product backlog and a velocity of 30 points per iteration. Taking into consideration that the iteration is
A team has 100 story points in the product backlog and a velocity of 30 points per iteration. Taking into consideration that the iteration is two weeks long, how many weeks does the team need to complete the backlog? 8 weeks 6 weeks 4 weeks 10 weeks