Question

1 Approved Answer

A Technical Solution Provider wants to sharpen their bid process based on a typical 85% learning rate for program installations which occur onsite at the

A Technical Solution Provider wants to sharpen their bid process based on a typical 85% learning rate for program installations which occur onsite at the client facility. The first module installation requires 1200 labor hours and the labor rate utilized is $65/hr which includes direct and indirect costs. The V.P. of Sales wants to sell installations in bundles of 5 modules using learning curve advantages. The slope for 85%learning curve is -0.234. The company uses a profit margin at 30% of cost.

Calculate the following details for the first order of five module installation. Use 4 decimal places in calculations. (Note: use a piece of scrap paper and provide the answers only in the space below).

a. Average manufacturing time per unit

b. Average cost per unit

c. Average price per unit that the customer expects to pay as it benefits from the learning curve concept.

Step by Step Solution

There are 3 Steps involved in it

Step: 1

blur-text-image

Get Instant Access to Expert-Tailored Solutions

See step-by-step solutions with expert insights and AI powered tools for academic success

Step: 2

blur-text-image

Step: 3

blur-text-image

Ace Your Homework with AI

Get the answers you need in no time with our AI-driven, step-by-step assistance

Get Started

Recommended Textbook for

International Marketing And Export Management

Authors: Gerald Albaum , Alexander Josiassen , Edwin Duerr

8th Edition

1292016922, 978-1292016924

More Books

Students also viewed these General Management questions

Question

How can collection classes be used when designing associations?

Answered: 1 week ago